Clearwater Lake LWD Placements
Objectives
There are several objectives of the Marjorie Creek
Restoration Project and they are outlined below.
- To increase the rainbow trout carrying capacity (rearing
and spawning habitat) through the addition of LWD (large woody
debris) instream structures in reaches DA1 and DA2.
- To document and present the structures that were placed
in Marjorie Creek.
- To calculate the anticipated increase in rainbow trout productivity
using established biostandards.
- To calculate the cost per structure site given labour and
materials costs.
To provide stream restoration training through on-ground
works to select local individuals.
FRBC Region/ MELP Region/ MoF
Region
Cariboo
Author
Michael A. Parker with excerpts from report by Peter
Nicklin, Bioterra Consulting
Proponent
Kleena Kleene Resource Association
Watershed
Clearwater Lake / Marjorie Creek
Location
The project area is located within the Chilcotin
Forest District of the Cariboo Region, some 230 km West of the
City of Williams Lake.
Introduction
With an active community group as proponent, all
levels of Fish Habitat, Riparian, and Upslope Assessments have
been completed for this watershed. MoF is working with the proponent
to complete road deactivation and upslope works.
Three key fish habitat issues guided restoration
options in the Clearwater Lake watershed.
-
Marjorie Creek is the major source of recruitment
for rainbow trout in the watershed (specifically the stream
below the bridge crossing at the Big Stick FSR).
-
The carrying capacity of Marjorie Creek (presently
limited to the lower four reaches, approximately 1.9 kilometers)
is a major factor in determining the status of the rainbow
trout population in the Clearwater Lake watershed
-
Fish habitat impacts to Marjorie Creek are
attributed to stream debris clearance, very low summer flows,
sedimentation of spawning gravel and low quantity of spawning
gravel. The removal of LWD in the Marjorie Creek system has
resulted in the degradation and loss of spawning habitat.
The loss of spawner holding pools and cover has probably further
reduced the suitability of a number of historic spawning sites.
Removal of LWD has increased the habitat favored by longnose
suckers. The suckers are competing with the rainbow trout
for spawning sites in the spring high flows. Increasing the
complexity of Marjorie Creek will enable the rainbow trout
to compete more successfully against the suckers for spawning
habitat.
Assessments and Prescriptions
The Kleena Kleene Resource Association (KKRA), through
Forest Renewal B.C. and in coordination with the Ministry of Environment
(Watershed Restoration Program) and Ministry of Forests, Cariboo
Region have completed an Overview and Level 1 Fish Habitat Assessment,
Sediment Source Survey, Interior Watershed Assessment, Level 2
Fish Habitat Assessment and Prescriptions Procedure (FHAP), Riparian
Assessment and an Integrated Watershed Restoration Plan on the
Clearwater Lake watershed.
The target species for restoration in the Clearwater
Lake watershed is rainbow trout (Oncorhynchus mykiss).
The Marjorie Creek system (downstream of the Big Stick FSR bridge)
is the primary source of recruitment for rainbow trout (spawning
and rearing) to Clearwater Lake and is thus the focus of in-stream
restoration. Lack of LWD in reaches DA1 and DA2 was determined
by the Level 2 FHAP to be limiting rainbow trout habitat.
Rehabilitation Work
Seven types of LWD structures (21 in total) were
placed over a 1.4km length of stream. The seven types of structures
included: Single log deflector, Double log deflector, bar stabilization
with rootwad LWD, Boulder/cobble weir, Deflector/digger log, Full
spanning digger log and Angled LWD.
All work was completed by a hand crew of three people,
with hand tools and a chainsaw. The breakdown of each structure
type is as follows: 6 angled/anchored LWD structures; 2
deflector/digger log structures; 1 downstream boulder/cobble
weir; 6 full spanning digger logs; 2 single log
deflectors; 6 buried LWD rootwad structures; and 1
double log/boulder deflector. Formation of local scour pools and
increased cover via log deflectors, digger logs, angled/anchored
LWD, bar stabilization with rootwad LWD and rock weir placements
should increase the carrying capacity of the stream by increasing
the rainbow trout rearing and spawning habitat through increased
stream complexity. Formation of scour pools will help retain more
water during periods of low flow and potentially increase fry/juvenile
survival.
Twelve person days of labour were created by the
Marjorie Creek rehabilitation project.
Cost Summary
The instream structures were completed in 24 hours.
Man hours of employment created by this project are calculated
by the following breakdown. 3 people were used for 24 hours. An
additional 2 people were used for the first 12 hours of labour.
12 man days (based on 8 hour days) of labour were created by this
project. Total labour costs for the 24 hours of construction were
$2,952.00. Equipment rental and supplies costs were $800.00. The
total cost of the installation of the instream structures is $3,752.00.
The cost of each structure is the total cost of labour, equipment
rental and supplies is $3,752/21 structures. Each structure has
an estimated average cost of $178.67.
Restoration Results
Twelve pieces of LWD were added to Reach DA2, thus
exceeding the total pieces of wood recommended for addition in
the Level 2 FHAP. The expected increase in rainbow trout population
(using established biostandards) is 2.7 fold for total rainbow
trout numbers and a 1.3 fold increase for catchable sized trout
(>= 15 cm) per unit length of mainstem.
Proposed Work
No further works are proposed for the Clearwater
Lake Watershed.
For Further Information contact:
Michael A. Parker
Ministry of Environment and Parks
400-640 Borland St.
Williams Lake, BC
V2G 4T1
Tel.(250)398-4696 Fax.(250)398-4214 |
Ken Jansen
Kleena Kleene Resource Association
General Delivery Kleena Kleene, BC
V0L 1M0
Tel. (250) 476-1195 |
Site 8 on Marjorie Creek at extreme low flows
during August 1998 installation and approaching bank full conditions
on November 12, 1998.