Woodjam Creek Culvert
Access
Objectives
To restore fish passage at this mainstem culvert
crossing for all life stages of the target species.
FRBC Region/ MELP Region/ MoF
Region
Cariboo/Cariboo/Cariboo
Author
Michael Parker
Proponent
Weldwood of Canada Ltd., Williams Lake Division
Watershed
Woodjam Creek
Location
Woodjam Creek is a tributary to the Horsefly River.
A wide range of species including anadromous species utilize the
majority of this watershed that is located approximately 25 km
East of the community of Horsefly, in the Horsefly Forest District.
Introduction
This project was undertaken to address concerns
within the proponents operating area as identified through an
assessment conducted by another licensee. As WRP is meant to be
conducted on the watershed scale it often does addresses issues
for more than one operator, and as such operators in this case
chose to address identified projects individually.
Assessments and Prescriptions
Minimal Assessments have been conducted in this
watershed on fish or riparian habitat. However, a Fish Passage
Culvert Inspection was completed in 1998 by Bioterra Consulting
for Riverside Forest Products, Soda Creek Division. As part of
this watershed is in the operating area of Weldwood of Canada
Ltd., this firm proceeded with the replacement of the one high
priority identified barrier within their area of the watershed.
This replacement provides access to 3.6 km of high value fish
habitat, not including tributaries above this mainstem crossing.
The existing culvert was determined to be undersized
for the crossing according to Forest Practices Code requirements
as the 1400mm culvert was not adequate for high flows on the 2.3m
bankfull channel. It is expected that velocities impact adult
migration during spawning periods, as well as juvenile passage.
Rehabilitation Work
The old 1400mm culvert was replaced with a full
spanning bridge structure. Fill was pulled back and the channel
around the bridge abutments armoured. Gradient through this area
was approximately 1.5%.
Cost Summary
Item
|
Cost
|
Materials
|
$44,000
|
Labour
|
$3,000
|
Machinery
|
$6,000
|
Total*
|
$53,000
|
*budget is estimated based on similar project activities
at other locations.
Restoration Results
Over 3.6 km of mainstem habitat is now accessible
to all life stages of fish. As well, tributaries above the crossing
will be accessible from the mainstem for rearing. The mainstem
itself is approximately 2.3 meters bankfull at the crossing, and
provides a variety of rearing and spawning upstream of the crossing.
Proposed Work
Level 1 FHAP Assessment and in stream works are
scheduled to begin in Woodjam Creek during 1999.
For Further Information contact:
Brian Chapman
Ministry of Environment and Parks
400-640 Borland St.
Williams Lake, BC
V2G 4T1
Tel.(250)398-4550 Fax.(250)398-4214
Or
Karen Campbell
Weldwood of Canada Ltd.
P.O. Box 4509
Williams Lake, BC
V2G 2V5
Tel. (250)392-7731