SHEEMAHANT WATERSHED

OVERVIEW FISH HABITAT ASSESSMENT

MARCH, 1998

 

 

 

Prepared by

Judy E. Hillaby

 

 

under contract to

Western Forest Products

P.O. Box 820,

100 E. Ludlow,

Ladysmith, B.C.

V0R 2E0

 

for submission to

Ministry of Environment, Lands and Parks,

680 Borland Street,

Williams Lake, B.C.

V2G 4T1

 

 

A program conducted through the auspices of Forest Renewal B.C.,

Contract # CCA - 856

 

1.0 EXECUTIVE SUMMARY

 

 

 

2.0 ACKNOWLEDGMENTS

Special thanks are due to Ardice Neudorf, Naomi Tabata and the other staff at Madrone Consultants Ltd. who conducted the background research and initial overview assessment. Bob Brand and Bill Dwyer of Western Forest Products in Ladysmith, Percy Walkus of the Oweekeno Nation, as well as Mike Parker and Troy Larden of the Ministry of Environment, Land and Parks in Williams Lake, all participated in ensuring that this project was properly initiated and brought to its conclusion. Their encouragement and direction is appreciated.

TABLE OF CONTENTS

1.0 EXECUTIVE SUMMARY

2.0 ACKNOWLEDGMENTS

3.0 BACKGROUND AND OBJECTIVES

4.0 METHODS

5.0 FINDINGS

5.1 Watershed Characteristics

5.2 Salmonid Species Present

5.3 Fish Distribution

5.4 Habitat Concerns

6.0 APPROACH

6.1 Field Examination Priorities

6.2 Initial Restoration Strategy

6.3 Field Strategy

7.0 LIST OF REFERENCES

8.0 LIST OF CONTACTS

9.0 LIST OF ABBREVIATIONS

10.0 APPENDICES

 

SHEEMAHANT RIVER

OVERVIEW FISH HABITAT ASSESSMENT

________________________________________________________________________

 

3.0 BACKGROUND AND OBJECTIVES

At the request of Pacific Forest Products, Forest Renewal B.C. has provided funding to undertake an Overview and Level I Fish Habitat Assessment on the Sheemahant River. With the cooperation of the Oweekeno Nation and with the technical assistance of Madrone Consultants Ltd. this work was initiated in the summer of 1997, in anticipation of field work in the fall of the same year. This document contains the results of the Overview Assessment. Results of the Level I Fish Habitat Assessment are contained in a separate report. The objectives of the overview assessment are:

The overview assessment uses existing or easily obtained information to provide a preliminary indication of the factors that limit fish production in the watershed. The purpose of this is to focus field assessment and preliminary restoration plans on areas where substantial benefits to the fishery resource are likely.

 

4.0 METHODS

Methods were consistent with those described in the Watershed Restoration Program Technical Circular No. 8. Most information came from DFO, as a part of continuing salmon escapement records that have been undertaken for many years. Anecdotal information was gathered from several sources, but all had been consolidated previously into the government sources.

FISS and SISS data systems were searched in order to obtain the most recent fish distribution information, which was transposed onto 1:20,000 scale TRIM maps. Escapement information was obtained from DFO, but recent years’ data was not available for the study area. Recent (1991), colour airphotos were provided by Pacific Forest Products that covered their operating area, and other airphotos (black and white, 1979) were also made available for the headwaters and upstream tributary zones. The mainstem Sheemahant and its significant tributaries (Kull Creek, Lemolo Creek and Sumquolt Creek) were divided into reaches, which were used to describe zones of homogenous stream character.

Further information was obtained from the field data recently gathered from FHIP studies done in the Sumquolt drainage earlier in 1997, and also from WRP Fish Habitat Assessment in Lemolo Creek (1996). This information is in the draft form, and is not to be quoted without the consent of MOELP, and the author.

5.0 FINDINGS

5.1 Watershed Characteristics

The Sheemahant River is characterized by shallow gradient with the predominant channel morphology type being glide. Oreographic lifting, rain on snow events and large, warm weather systems results in a dramatic rise and fall in discharge. As the system rises, wetlands surrounding the mainstem become flooded. These wetlands which also serve as catchment areas for runoff from the surrounding mountains regulate the mainstem’s discharge and sediment load.

The Sheemahant River is a glacially-fed system with high turbidity throughout most of the mainstem. This does not allow for good observation of individual fish or fish habitats. Tributaries, sidechannels and off-channel habitats where fish were visually identified, are characterized by clear water and good flow.

The Sheemahant River is found in the Coastal Western Hemlock zone which encompasses three biogeoclimatic subzones. The Central Moist Submaritime Coastal Western Hemlock Variant (CWH ms2) subzone occurs in the lower elevations (below 700m) of the Sheemahant River. At 700 to 1000m, the Montane Wet Submaritime Coastal Western Hemlock Variant (CWH ms2) occurs. The Windward Moist Maritime Mountain Hemlock Variant (Mhmm1) is found at upper elevations. In the headwaters, total snowfall is usually high, which can result in substantial snowpacks that may persist well into July. Large glaciers at the head of this drainage produce cold air that can influence the climate.

Increase in peak flows from logging related activities can increase the amount of fine sediments that are added to the mainstem. In the Sheemahant watershed, surrounding steep hills with low gradient wetlands adjacent to the mainstem could be corridors for distribution of sediment into spawning areas, and also affect woody debris and nutrient disbursement. Further studies should be initiated to determine to what degree the fish stocks of the Sheemahant River are being affected by hydrological impacts.

5.2 Salmonid Species Present

Rivers Inlet has been the home of important commercial fisheries, and numbers of sockeye salmon spawners have been documented by DFO for several decades. In recent years, a clear decline in the number of sockeye has been recorded, prompting increased research and attention to possible contributing factors. Initial indications are that there are complex processes at work, including the possibility of changing marine environments, and other factors well outside the watershed study areas. Although there is no clear evidence that this is the case, we are assuming that the quality and quantity of fish habitat in the Sheemahant River is part of the declining sockeye experience.

There are 4 other anadromous species recorded in the Sheemahant River. These include coho, chinook, pink and chum salmon, but not steelhead trout. Directed spawner counts have not been attempted on these species, due to the very turbid, glacial water in the mainstem making these species difficult to spot in aerial surveys. The presence of the fish is known; however, precise spawning areas, timing, population trends and factors affecting them are unknown. It is assumed that any negative effects on fish habitat on the lower mainstem would have a negative effect on all the anadromous fish present there.

Rainbow and cutthroat trout, as well as Dolly Varden, are present in the mainstem and its peripheral areas. There have been no habitat surveys, creel surveys, lake stocking or other management or enhancement activities directed on these stocks. None of these populations receive any significant harvesting activity from either sport or aboriginal fishing.

5.3 Fish Distribution

The Sheemahant River is accessible to anadromous fish to the cascades just upstream of its confluence with Lemolo Creek (about 20km). Most anadromous fish habitat is confined to the mainstem until this point. Although anadromous fish have access to at least 1 km of the lower part of Lemolo Creek (a complete barrier exists at 5 km), the fish habitat is poor and fish distribution is probably limited to spawner incursions for a short distance upstream of the confluence. The primary spawning area for anadromous fish (and probably many resident fish as well) is in Reaches 1 to 6 of the mainstem Sheemahant, where abundant gravel bars and sidechannel habitats exist. These side channels also provide slow-water backwaters, which allow for juvenile rearing, adult holding and spawning areas, and generally, refuge habitats from extreme flow events which are frequent in this system.

Tributaries to the mainstem Sheemahant River also provide some fish habitat, although this appears limited to the short confluence areas, off the side hill. These tributaries are valuable sources of clear water and some nutrients, and where they are accessible to fish, also function as refuge habitat from floods in the mainstem.

More stable in-stream habitat is provided by the tributaries far upstream, including Hilder and Marvel Creeks; however, there is a barrier further downstream on the Sumquolt Creek that seems to prohibit fish access into these areas. The upper Sheemahant River, above the Sumquolt confluence, contains attractive, low-gradient habitat and may be inhabited by coho and Dolly Varden into the extreme headwaters.

DFO notes that this barrier (at 20 km on the mainstem) is a "passable cascade"; and this is confirmed by recent field work this year indicating the presence of coho above this barrier.

The uppermost limit of fish in the mainstem Sheemahant has not been documented, and anadromous fish access should be assumed up to the lip of the glacier.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 1. Sheemahant River Watershed

 

5.4 Habitat Concerns

Fish habitat concerns are focused on Reaches 1 to 6, which are accessible to all salmonids. Habitat concerns in Reach 1 fall into 3 categories:

  1. The west main road on the right bank has been deactivated, but may have cut off or destroyed the riparian zone of peripheral fish habitats in sidechannels and sloughs
  2. The mainline road on the left bank is active and well-maintained, but has cut off access to sloughs and low-gradient fish habitat behind the road. These may provide opportunities for sidechannel development
  3. Eroding banks and destruction of the riparian zone along the mainstem river, as well as tributaries crossing blocks adjacent to the mainstem.

Reach 7 and above in the mainstem do not now have any logging activities in the watershed, and so are of no interest when judging the impact of forest development activities on fish habitat. There are now road-building and harvesting activities in the lower Sumquolt drainage and there is at least one old block near the confluence with the Sheemahant. Above this point, there are no apparent concerns for fish habitat and it is inappropriate to include these areas in this report.

 

6.0 APPROACH

6.1 Field Examination Priorities

In order to locate impacted areas more precisely, the lower reaches have been subdivided into sections, and then ranked for field examination priority.

 

Table 1. List of fish habitat concerns and possible habitat restoration opportunities in the lower Sheemahant River.

Reach

Section

Comment

Priority

1

1

Active, unstable area close to camp. Should be left alone.

LOW

 

2

Check the bank condition near the road crossing, re: erosion control.

LOW

 

3

Tributary off the sidehill may be affected by the road crossings. Possible sidechannel development.

MEDIUM

 

4

Right bank slope condition (erosion) and tributaries through the block may be impacted.

HIGH

 

5

Right bank slope condition (erosion) and tributaries through the block may be impacted. Also, on the left bank may be a sidechannel development opportunity.

HIGH

 

6

Check the condition of the west main road on the right bank, especially the tributary crossings and confluence areas with the mainstem.

HIGH

2

1

Thin riparian zone on both banks, and the tributary confluence on the left bank. Check below the mainline on the left bank.

HIGH

 

2

Sidechannel development on the left bank, and the thin riparian zone on the right bank. Check behind the mainline on the left bank for fish habitat.

HIGH

 

3

There is a tributary through the block on left bank. Determine its condition through the block, and at the mainstem confluence.

HIGH

 

4

Road is adjacent to the stream. Check for impacts.

LOW

3

1

Tributaries and road crossing on the left bank. The road crossings should be checked, especially behind the mainline. The block with tributaries through it, should check the tributary confluence zones, and the slumping bank on the right bank.

HIGH

 

2

Sidechannel development on the left bank may be possible.

MEDIUM

4

1

West main road, right bank, should be checked re: road crossings and sidechannel development, especially behind the mainline.

HIGH

 

2

Left bank sidechannel development possibility. Check behind the mainline at the toe of the slope.

HIGH

5

1

Riparian zone on the right bank may have been damaged.

MEDIUM

 

2

Sidechannel development on the right bank. There may be a thin riparian zone on the left bank.

MEDIUM

 

3

Tributary crossings, sidechannel development on the left bank, check behind the mainline. Right bank, road crossings over the tributaries, sidechannel development.

VERY HIGH

6

1

On the right bank, check the downstream condition of the tributaries

MEDIUM

 

2

Left bank, has been previously addressed in Lemolo Creek WRP FHAP. Check behind mainline for sidechannel development opportunities. Condition of tributaries.

LOW

 

3

No evidence of impacts

LOW

Kull Cr.

1

Check the lower area for bank stability, road impacts and tributary condition.

HIGH

 

6.2 Initial Restoration Strategy

6.2.1 Sidechannel Development

Sidechannel habitats that improve fish habitat have controlled flow, stabilized banks, graded gravel, LWD at strategic points, and complex in-stream habitat. Spawning channels may have upstream dams with control over the entire stream. Others have engineered flow control works off the mainstem, at the upstream end of the developed sidechannel. Others rely more on excavated areas of naturally-upwelling groundwater that appears in old flood channels adjacent to the river mainstem. The target fish species and life stages also dictate optimum flow regimes, substrate, cover pattern, etc. The most critical factor is obtaining controlled flow and in identifying the limiting factor for each fish species, so that each project is custom-designed, both in terms of hydraulic design as well as fish habitat requirements.

Earlier WRP work conducted in Lemolo Creek obtained a professional engineering opinion indicating the mainstem of the Sheemahant was too unstable to design sidechannel development works. In a practical sense, areas adjacent to the mainstem either had an unmanageable amount of material to move, or would be too flood-prone for effective flow control. Instead, the focus should be on identifying areas that are sheltered from flood events by being behind the mainline road, set back at the toe or the slope, or possibly depressions that have been isolated by large berm buildups. Biological work to identify potential fish rearing areas (current and those possibly cut off in the past) would identify where fish habitat is located now, which species inhabit those areas, and correlate fish presence with specific sidechannel conditions. This information should complement engineering studies (future work) based on airphoto interpretation to identify those areas where flow control works would be feasible to construct. This fits the requirement of a Level I Fish Habitat Assessment.

6.2.2 Tributary Rehabilitation

Past logging practices often did not recognize the importance of tributary streams to mainstem fish habitats, especially non-fish bearing streams. These tributaries have been damaged by logging practices through destruction of the riparian zone, bank and gully wall destabilization causing bedload movement into the mainstem habitat, and by obstruction or inundation of the confluence area, where small but important off-channel habitats exist.

Where the riparian zone has been destroyed, or the gully sidewalls destabilized, the strategy is to identify those specific areas, so that a riparian specialist team can conduct site-level surveys in the spring (future work), for streamside planting, LWD placement or other reconstruction later in the 1998 season. Where off-channel habitat has been cut off or inundated such that no re-construction is possible, a quantity and type of off-channel fish habitat will be identified for creation in another location.

6.2.3 Slope Stability

This study will identify areas where eroding banks and upslope stability affect the mainstem fish habitat. This process is usually evident in the substrate material and island/channel formations downstream, and sometimes this is also correlated with a more specific loss of (for example) spawning gravel through gravel compaction, aggradation, etc. Usually, gradual, more subtle changes in channel hydraulics are noticed as the assessment crew walks upstream, and these changes should be noted in the Fish Habitat Assessment Form.

It is beyond the scope of this study to identify the causes and extent of bank and slope instability; however, the Level I FHAP can identify the specific locations where valuable fish habitat is threatened and help prioritize upslope stabilization activities, and bank stabilization projects, where advised.

The west main road network up the right bank of the Sheemahant is a case where the road deactivation may be completely suitable from an engineering viewpoint, but the fisheries effectiveness may be lacking. A field inspection of each tributary crossing will determine an appropriate course of action with reference to WRP road deactivation planning.

6.3 Field Strategy

Field studies will focus on:

 

 

Table 2. Number of crew-days required to survey each reach and section of the Sheemahant River study area.

Reach

Section

km length

MS (2 crews)

Tribs (1 crew)

1

1

1.7

1.7

0.5

2

0.4

0.4

0.2

3

1.2

1.2

0.3

4

0.4

0.4

0.1

5

1.4

1.4

1.2

6

0.7

0.7

0.3

2

1

0.4

0.4

0.6

2

0.6

0.6

0.3

3

0.4

0.4

0.6

4

0.6

0.6

0.6

3

1

1

1

0.4

2

1.3

1.3

0.7

4

1

1.8

1.8

0.9

2

0.6

0.6

0.4

5

1

0.5

0.5

0.2

2

0.8

0.8

0.8

3

1.2

1.2

1.2

6

1

1.3

1.3

0.5

2

1.2

1.2

0.5

3

0.8

0.8

0.4

Kull Creek

1

1

1

0

19.3

10.7

 

It is proposed that field surveys focus on high and medium priority reaches and sections; however, some flexibility must be maintained to allow for variable field conditions. There should be ten (10) field days allocated to this watershed, assuming both aircraft and ground-based field support.

 

 

7.0 LIST OF REFERENCES

 

Britton, E.W. and D. E. Marshall. 1980. Catalogue of Salmon Streams and Spawning Escapements of Statistical Area 9 and 10 (Rivers and Smith Inlets). Canadian Data Report of Fisheries and Aquatic Sciences No. 222. xvi+ 164pp.

Hillaby, J.E. and A. Neudorf, 1998 (in preparation). Sheemahant Watershed Level I Fish Habitat Assessment Volume I - Summary. Report prepared under contract to Western Forest Products and Ministry of Environment, Lands and Parks, Williams Lake.

Hillaby, J.E. and A. Neudorf, 1998 (in preparation). Sheemahant Watershed Level I Fish Habitat Assessment Volume II - Data Appendices. Report prepared under contract to Western Forest Products and Ministry of Environment, Lands and Parks, Williams Lake.

Hillaby, J.E., T. McIntosh, and J. Ebell, 1997. Lemolo Creek Watershed Fish and Riparian Habitat Assessments. Report prepared under contract to Pacific Forest Products and Ministry of Environment, Lands and Parks, Williams Lake. 39pp and Appendices.

J. Hillaby, 1998. (in preparation). Reconnaissance Level Fish Habitat Inventory for the Upper Machmell, Sumquolt and Phinney Creek watersheds. Report prepared under contract to Western Forest Products and Ministry of Environment, Lands and Parks, Williams Lake.

Johnson, N.T. and P.A. Slaney, 1996. Fish Habitat Assessment Procedures Watershed Restoration Technical Circular 8, revised April 1996. Watershed Restoration Program; Ministry of Environment, Land and Parks, and Ministry of Parks.

Larkin, G.A. and P.A. Slaney. 1996. Calibration of a Habitat Sedimentation Indicator for Use in Measuring the Effectiveness of Watershed Restoration Treatments. Province of British Columbia, Ministry of Environment, Lands and Parks and Ministry of Forests. Watershed Restoration Management Report No. 5.

Pendray, T. 1988. Biophysical Inventory of Tributaries to Owikeno Lake - 1984 - 1985. Department of Fisheries and Oceans, Fisheries Branch, North Coast Division, Habitat Managmeent Unit, Prince Rupert, B.C.

SHIP Environmental Consultants. 1992. Stream Summary Catalogue for Subdistricts 9, Rivers Inlet and 10, Smith Inlet. Report prepared under contract to DFO/MOELP Fish Habitat Inventory and Information Program.

 

 

 

8.0 LIST OF CONTACTS

Sandy McLaurin, CID Community Advisor

Fisheries and Oceans Canada

P.O. Box 340,

Hagensborg, B.C. V0T 1H0

250-982-2663

Brad Koroluk, Habitat Technician,

Fisheries and Oceans Canada

P.O. Box 130,

Bella Coola, B.C. V0T 1C0

250-799-5729

Bob Brand, Divisional Engineer

Western Forest Products

P.O. Box 820, 100 E. Ludlow

Ladysmith, B.C. V0R 2E0

250-245-8211

Steve Bachen, Fisheries Technian,

Fisheries and Oceans Canada

Pacific Biological Station

P.O. Box 100,

Nanaimo, B.C. V9R 5K6

250-756-7174

Dennis Rutherford, Stock Assessment Biologist,

Fisheries and Oceans Canada

Pacific Biological Station

P.O. Box 100,

Nanaimo, B.C. V9R 5K6

250-756-7174

Ken Dunsworth, Forest Ecosystem Specialist,

Ministry of Environment, Lands and Parks,

P.O. Box 190,

Hagensborg, B.C. V0T 1H0

250-982-2064

Dave MacLain, Engineer,

Northwest Hydraulic Consultants Ltd.

North Vancouver, B.C.

604-980-6011

 

9.0 LIST OF ABBREVIATIONS

 

ABBREVIATION

DESCRIPTION

FHIP

Fish Habitat Inventory Program

DFO

Fisheries and Oceans Canada

WRP

Watershed Restoration Program

MOELP

Ministry of Environment, Lands and Parks

FHAP

Fish Habitat Assessment Program

LWD

Large Woody Debris

 

 

10.0 APPENDICES

APPENDIX 1

FISH DISTRIBUTION SUMMARY FORM

APPENDIX 2

OVERVIEW ASSESSMENT HABITAT CONDITION SUMMARY FORM

APPENDIX 3

OVERVIEW ASSESSMENT PRELIMINARY HABITAT ASSESSMENT FORM

Overview Assessment - Preliminary Habitat Assessment Form

Watershed Name: SHEEMAHANT RIVER UTM Coordinates: _______________________

Watershed Code: 910-1288-798-535 NTS Maps: _______________________

Reach

Section

Habitat

Value

Upslope Impact

Potential

Major Impacts

Priority

Restoration

Opportunities

1

1

H

M

Active, unstable, flooded area

Low

Flood protection concerns

1

2

H

H

Bank condition degraded; road design

Low

Upslope stability, erosion control

1

3

H

H

Tributary confluence compromised by road.

Medium

Sidechannel development

1

4

H

H

RB slope instability, tributary degraded

High

Upslope stability

1

5

H

H

RB slope instability, LB off-channel habitat lost

High

Sidechannel development

1

6

H

H

West main road degraded tributary mouths

High

Road re-design/deactivate

2

1

H

H

Riparian zone compromised, tributary mouth degraded

High

Riparian restoration, road re-design

2

2

H

H

LB fish habitat cutoff, RB riparian zone lost

High

LB sidechannel development

2

3

H

H

Kull Creek riparian zone lost, confluence degraded

High

Riparian restoration, road re-design

2

4

H

H

Road adjacent to stream; erosion, training

Low

Riparian restoration

3

1

H

H

LB tributaries compromised by road; RB unstable bank

High

Road re-design/deactivate

3

2

H

H

LB sidechannel may be cutoff, riparian compromised

Medium

Sidechannel development

4

1

H

H

RB west main road degraded tributary mouths

High

Road de-activate

4

2

H

H

LB wetlands cutoff by road

High

Re-open habitat, sidechannel development

5

1

H

H

RB riparian zone compromised;

Medium

Road de-activate, riparian restoration

5

2

H

H

LB riparian zone compromised; RB off-channel habitat lost

Medium

Riparian restoration; sidechannel developments

5

3

H

H

Tributary crossing degraded; cutoff rearing habitat

V. High

Riparian restoration; sidechannel developments

6

1

H

H

RB tributary mouths degraded

Medium

Riparian restoration;

6

2

H

H

LB off-channel habitats cutoff by road

Low

Develop/extend off-channel habitat

6

3

H

H

No evidence of impacts

Low

---

7

1

H

H

No evidence of impacts

Low

---

8

1

H

H

No evidence of impacts

Low

---

Overview Assessment - Preliminary Habitat Assessment Form

Watershed Name: KULL CREEK UTM Coordinates: _______________________

.

Watershed Code: 910-1288-798-102 NTS Maps: 92M.068, 78 .

Reach

Section

Habitat

Value

Upslope Impact

Potential

Major Impacts

Priority

Restoration

Opportunities

1

H

High

Riparian zone lost; degraded tributary mouth

H

Riparian restoration; in-stream habitat improvement

2

L

High

Riparian zone lost; upslope stability

M

Riparian restoration; upslope stability

3

L

High

No impacts visible in airphoto

L

----

APPENDIX 4

ANNUAL SALMON ESCAPEMENT DATA

Year

Sockeye

Chinook

Coho

Chum

Pink

Steelhead

1948

UNK

         

1949

UNK

         

1950

57500

 

UNK

     

1951

45000

 

UNK

     

1952

75000

         

1953

35000

0

0

0

0

UNK

1954

UNK

UNK

UNK

UNK

UNK

UNK

1955

UNK

0

0

0

0

UNK

1956

35000

0

0

0

0

UNK

1957

35000

UNK

0

0

0

UNK

1958

UNK

UNK

0

0

0

UNK

1959

75000

UNK

0

0

UNK

UNK

1960

UNK

UNK

0

0

UNK

UNK

1961

35400

UNK

0

0

UNK

UNK

1962

42500

0

0

0

0

UNK

1963

82500

3500

0

0

UNK

UNK

1964

110000

UNK

0

0

N/O

UNK

1965

15000

UNK

0

0

0

UNK

1966

50000

200

0

0

0

UNK

1967

135000

25

0

0

UNK

UNK

1968

75000

UNK

0

0

UNK

UNK

1969

75000

3500

0

0

200

UNK

1970

7500

3500

0

0

UNK

UNK

1971

6000

2000

0

0

N/O

UNK

1972

32500

1000

0

0

0

UNK

1973

250000

UNK

0

0

75

UNK

1974

137500

1500

UNK

0

75

UNK

1975

35000

N/O

N/O

0

N/O

UNK

1976

20000

50

0

0

N/O

UNK

1977

27500

UNK

0

0

25

UNK

1978

150000

800

UNK

0

100

UNK

1979

65000

200

N/O

0

N/O

UNK

1980

61000

2000

0

0

0

UNK

1981

200000

1000

0

0

N/O

UNK

1982

150000

200

0

0

0

UNK

1983

125000

500

0

0

0

UNK

1984

25000

8500

N/O

N/O

N/O

UNK

1985

135000

500

N/O

N/O

N/O

UNK

1986

325000

500

UNK

UNK

UNK

UNK

1987

100000

500

0

0

0

UNK

1988

200000

N/O

0

0

0

UNK

1989

125000

UNK

UNK

UNK

UNK

UNK

1990

16000

0

0

0

0

 

1991

10000

0

N/I

0

0

 

1992

20000

N/I

N/I

0

0

 

1993

80000

N/I

N/I

0

N/I

 

1994

50000

UNK

UNK

UNK

UNK

 

1995

100000

N/O

UNK

N/O

N/O

 

1996

300000

N/O

UNK

N/O

N/O

 

 

APPENDIX 5

FISS SEARCH RESULTS

11.0 OVERVIEW MAP