Ministry of Agriculture & Lands
SDLC
STANDARDS
QUALITY ASSURANCE
GUIDELINES
Version
1.1 July 9, 2004
This page contains the published standards for the Ministry's approach to Quality Assurance Guidelines.
1. INTRODUCTION
1.1 Purpose
1.2 Audience
1.3 Scope/Exclusions
1.4 Assumptions
1.5 Other
Standards
2. THE
QUALITY ASSURANCE TEAM
2.1 General
2.2 Applications
Architect (AA)
2.3 Application
Manager (AM)
2.4 Business
Analyst (BA)
2.5 Business
Expert
2.6 Data
Administration (DA)
2.7 Database
Administrator (DBA)
2.8 End
Users
2.9 Ministry
Project Manager (PM)
2.10 Vendor
3. SYSTEM DEVELOPMENT LIFE-CYCLE OVERVIEW
4. QA OF SYSTEM DEVELOPMENT LIFE-CYCLE DELIVERABLES4.1 QA of Planning Phase Deliverables
4.2 QA of Definition Phase Deliverables
4.3 QA of Requirements Phase Deliverables
4.4 QA of Design Phase Deliverables
4.5 QA of Build Phase Deliverables
4.6 QA of Implementation Phase Deliverables
4.7 QA of Warehouse Phase Deliverables
4.8 QA of Deliverables During Maintenance
5. CONCLUSION
FIGURES
Figure 1:
SDLC Phases
Figure 2: SDLC QA Matrix
APPENDICES
Appendix A:
QA Matrix - Detailed
Appendix B: Bibliography
This section of the document records the various versions or releases of this document.
| Version | Details/Description | Distribution | Date | Author | Organization |
| 0.1 | First Draft | Whole Document | June 28, 2001 | Dawn Henry | IMB |
| 0.2 | Second Draft Deliverable Definitions Updated |
Whole Document | Aug. 13, 2001 | Dawn Henry | IMB |
| 0.3 | Third Draft Updated with changes from BA group |
Whole Document | Dec.19, 2001 | Dawn Henry | IMB |
| 1.0 | Published to the Web and Minor Changes | Whole Document | Dec.19, 2001 | Dawn Henry | IMB |
| 1.1 | Edits based on Final Report | Whole Document | July 9, 2004 | Chris Burd | Catchword Info. Design |
| Table 1: Version Control |
|
1. INTRODUCTION Project Quality Management is defined as the processes required to ensure that the project will satisfy the needs for which it was undertaken. This quality assurance (QA) processes document describes the processes for conducting quality assurance on the deliverables for application development and maintenance projects in the Ministry. This document does not replace the SDLC documentation but should be used in conjunction with it. 1.1 Purpose This document defines the activities performed to provide assurance that the application deliverables the Ministry receives conform to established Ministry standards. The QA guidelines also describe how the project will be quality assured to ensure that the policies, standards, practices, procedures, and processes applicable to the Ministry's System Development Life-Cycle (SDLC) are followed. 1.2 Audience This document is directed at those who will be producing deliverables as required for designing, developing and maintaining applications for the Ministry. This includes external vendors, consultants, and business partners, as well as Ministry employees. All vendors performing work for the Ministry are expected to follow the quality assurance processes as outlined in this document. This fact should be specified in the RFP and contract. 1.3 Scope/Exclusions These standards focus on corporate applications, but they can also be used for smaller applications, e.g., district or regional applications. In these instances the standards may be used as a guideline to the QA processes, but the QA processes as defined do not apply. The requirements for Government-wide applications are not included in this document. This document intends to ensure that vendors and staff have a clear understanding of the QA processes so they can be used in all Corporate application development and maintenance projects. This document includes detailed QA processes with required timelines and clear delineation of roles and responsibilities for Ministry staff and vendors. 1.4 Assumptions It is assumed that the audience is familiar with the Ministry's System Development Life Cycle (SDLC) Overview. 1.5 Other Standards Other related standards can be found on the Standards page. |
|
2.1 General Overall coordination of quality assurance is the responsibility of the Ministry Project Manager for most deliverables, except during the Maintenance phase, where this responsibility lies with the Application Manager. All feedback and QA results should be delivered to the originator of the deliverable via this coordinator. The QA coordinator should communicate appropriately with all team members with respect to the QA of deliverables. There are several roles associated with the various QA tasks. Individuals may assume multiple roles during the project, and roles may rotate when appropriate. This section provides a general description of the roles and responsibilities. Please refer to the appropriate section for the specific QA. Several deliverables will require both a Business QA and a Technical QA. Note: The person performing the QA should not be the person who developed the deliverable. 2.2 Application Architect (AA) The Application Architecture Section provides advice on QA applications from a technical perspective.The Application Manager is the Ministry person responsible for the overall management of one or more applications. A key quality assurance role is to ensure the QA of an application by leading and conducting the User Acceptance Testing.
This description applies to the Information Management Branch Business Analyst (IMB BA).
Note: For the purposes of this document, Information Management Business Analyst could refer to either the Information Business Analyst or the Information Business Systems Consultant, as assigned to the client or project. 2.5 Business Experts The Business Experts are responsible for the QA of deliverables from a business perspective. Data Administration group is responsible for QA of the UML Domain model, CASE Repository and the Logical Data Model.2.7 Database Administrator (DBA) The Database Administrator is responsible for the QA application code, physical database, application delivery, scripts and process.2.8 End Users The End User will assist in the QA of specific deliverables from the user's perspective.2.9 Ministry Project Manager (PM) The Ministry Project Manager is responsible for overall coordination of the QA for all deliverables, except those in the maintenance phase, which are usually managed by the Application Manager. The duties are as follows:
2.10 Vendor The contractor is often referred to as the Vendor. The Vendor is responsible for ensuring the deliverable meets the Ministry standards prior to submitting it to the Ministry Project Manager or Application Manager. The Vendor will also review QA results as performed by the Ministry staff and make changes to the deliverable where required. |
||||||||||||||||||||||||||
|
3. SYSTEM DEVELOPMENT LIFE CYCLE OVERVIEW The foundation for this QA guideline is the System Development Life Cycle (SDLC). The SDLC consists of seven distinct Phases as shown in Figure 1 below. For more information on these phases see the Systems Development Life Cycle Standard. |
| Phase 1 | Phase 2 | Phase 3 | Phase 4 | Phase 5 | Phase 6 | Phase 7 |
| Planning | Definition | Requirements | Design | Build | Implementation | Warehouse |
Each Phase has one or more individual deliverables associated with it. These deliverables are described in other standards documents. The QA processes for each deliverable are summarized in table format at the beginning of each phase. The complete table is located in Appendix A. |
4. QA OF SYSTEMS DEVELOPMENT LIFE CYCLE DELIVERABLES This section details the QA processes for each deliverable. Project Plans must include the timelines, costs and resources for these processes. Note: Where a time frame of 1 day is indicated, this means that a walkthrough or meeting is to be held for the purpose of performing the QA on that deliverable. Where possible, the deliverable should be supplied in advance. 4.1 QA OF PLANNING PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Proposal | ||||||||||||||||||||||||||||||||||||||||||||||||||
The Project Proposal is largely an internal document developed by Ministry staff prior to the enlistment of a vendor. In most cases it is developed by the Application Manager or the Ministry Project Manager. The Project Proposal should be developed ahead of the annual planning process or as needed throughout the year. For more details please refer to the Ministry developed standard for the Project Proposal. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Project Proposal is distributed via email or hardcopy to the Information Management Business Analyst, for the purpose of being quality assured. The QA results will be delivered to the author of the Project Proposal via email, phone or meeting.
|
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Project Proposal is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Project Proposal will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry Standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | format. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Request For Proposal | ||||||||||||||||||||||||||||||||||||||||||||||||||
| A Request for Proposal (RFP)is a request to suppliers to submit
proposals on how (and at what price) they would provide goods
and/or services. Details of the RFP process are in the Ministry RFP
Guide and at the Purchasing
Commission website. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The RFP is distributed via email or hardcopy to the Information Management Business Analyst for the purpose of being quality assured. The QA results will be delivered to the author of the RFP via email, phone or meeting.
|
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the RFP is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The RFP will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry Standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | details; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | omissions. | |||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | 1 - 2 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Invitation To Quote | ||||||||||||||||||||||||||||||||||||||||||||||||||
An Invitation to Quote (ITQ) is a written request made to prospective
suppliers to quote on goods or services sought by the prospective
purchaser. Details of the ITQ process are at the Purchasing
Commission website. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The ITQ is distributed via email or hardcopy to the Information Management Business Analyst for the purpose of being quality assured. The QA results will be delivered to the author of the ITQ via email, phone or meeting.
|
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the ITQ is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The ITQ will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry Standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | details; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | omissions. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | 2 - 3 days. |
|||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.2
QA OF THE DEFINITION PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Statement | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The purpose of the Project Statement is to provide a "road-map"
for the successful execution of a project. Refer to the Project Statement Standard documentation for a detailed description
of this deliverable. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Project Statement is distributed via email or hardcopy to the Information Management Business Analyst for the purpose of being quality assured. The QA results will be delivered to the author of the Project Statement via email, phone or meeting.
|
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Project Statement is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Project Statement will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | format. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | 1 - 2 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Schedule | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The
Project Schedule is a plan of the project's tasks. It details
the timelines and who is responsible for each task. It is part
of the Project Statement but for the purpose of this documentation
has been outlined as a separate deliverable. The Project Schedule,
where possible, will be done in MS Project. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Project Schedule is distributed (as part of the Project Statement)
via email or hardcopy to the Information Management Business Analyst
for the purpose of being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Project Schedule is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Project Schedule will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | deliverables and milestones are clearly defined; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | reasonability; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | level
of Ministry staff required (resources). |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | The Project Schedule should be quality assured at the same time as the Project Statement and the QA results returned to the Ministry Project Manager within 1 - 2 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Conceptual Design - High Level | ||||||||||||||||||||||||||||||||||||||||||||||||||
The Conceptual Design deliverable is a High Level document for
the Definition Phase, a Checkpoint in the Requirements Phase, and
the Mandatory in the Design Phase. The QA processes are the
same for all three phases. The deliverables, however, change
as they progress through the phases. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Conceptual Design is distributed via email or hardcopy to
the Information Management Business Analyst for the purpose of
being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Conceptual Design is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Conceptual Design will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical feasibility; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | fit with the Ministry infrastructure; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | review
of physical model. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One day. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.3
QA OF THE ANALYSIS PHASE DELIVERABLES
A standard has been developed for the Requirements Phase of the System Development Life Cycle. All vendors engaged to perform system requirements are instructed to follow and conform to these standards when producing deliverables for this phase. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Software Requirements Specification Document | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The Software Requirements Specification document will capture the analysis and documentation
of the business and functional requirements of the application
system, using data and process modeling techniques. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Software Requirements Specification Document is delivered as per Application Delivery Standards . The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Software Requirements Specification Document is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Software Requirements Specification Document will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical language; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | model soundness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | potential
for sharing with other projects. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | Two weeks. Where possible, the QA of this deliverable should be scheduled in advance to ensure availability of resources. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Oracle Designer Repository | ||||||||||||||||||||||||||||||||||||||||||||||||||
Oracle's Designer provides a central repository for the
storage of information about an application throughout its entire
life cycle. This repository enables consistent application design
and development within the Ministry. Standards for these deliverable
are located within the Data Architecture Standards plus the Oracle Repository Procedures documentation. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Oracle Designer Repository is delivered as per Application Delivery Standards . The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Oracle Designer Repository is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | business representatives for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA for the technical QA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Oracle Designer Repository will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | business requirements; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | descriptions; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness of repository; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | functional model soundness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | data
model soundness. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | The
QA result should be delivered to the vendor within two weeks via a meeting with the Ministry Project Manager. Note: This QA process will require three meetings: one for the technical QA, one for the business QA and a final meeting for the Ministry Project Manager to deliver the QA results to the vendor. |
|||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Data Conversion Analysis | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The Data Conversion Analysis document captures the analysis and
documentation of the current data and the requirements for importing
it into the new application. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The
Data Conversion Analysis is delivered as per Application Delivery Standards . The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Data Conversion Analysis is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant Business Area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Data Conversion Analysis will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | soundness of approach; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | data mapping; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | appropriate
testing strategy. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Conceptual Design - Checkpoint | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The Conceptual Design - Checkpoint is a review of the design,
to ensure the application will meet the business needs and work
within the Ministry's technical architecture. The QA processes
for this deliverable are defined in Conceptual
Design - High Level. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.4
QA OF DESIGN PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Conceptual Design - Mandatory | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The Conceptual Design - Mandatory is a required deliverable. The
QA processes for this deliverable are defined in Conceptual
Design - High Level. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Detailed Software Design Description | ||||||||||||||||||||||||||||||||||||||||||||||||||
The deliverable document from the Software Design Description process will include a set of technical specifications that will be used to generate (Build) and implement the new system or feature. The Detailed Software Design Description is quality assured via two walkthrough meetings - Business walkthrough and the Technical walkthrough. Each reviews the deliverable as noted below. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The
Detailed Software Design Description is delivered as per Application Delivery Standards. The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Detailed Software Design Description is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager for the business QA | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant business area staff for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | users for the business QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA for the technical QA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Detailed Software Design Description will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | fit with Ministry infrastructure; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | meets business needs as described in Software Requirements Specification Document; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | model soundness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | appropriate data mapping (where data conversion is required); | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | appropriate testing strategy; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical feasibility; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | technical
language. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | Two weeks. Where possible, the QA of this deliverable should be scheduled in advance to ensure the availability of resources. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Data Architecture Standards - Design | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The QA processes for this deliverable are defined in Data Architecture Standards in the Design Phase. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Data Conversion Design | ||||||||||||||||||||||||||||||||||||||||||||||||||
Data Conversion Design documentation will include a set of technical specifications that will be used to convert existing data and import it into the new system. Note: This deliverable is distributed and quality assured via walkthrough/meeting. It is to be quality assured at the same time as the Detailed Software Design System and using the same processes. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.5
QA OF BUILD PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Data Conversion Application | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The Data Conversion Application is the program and/or scripts
that convert the format of existing data structures into the structure
(as delivered by the Data Model) required by an application. This
would include dealing with incompatibilities (i.e. missing attributes
between the old and new data models). |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Data Conversion Application is delivered as per Application Delivery Standards . The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Data Conversion Application is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | end users; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DBA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Data Conversion Application will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | code structure conforms to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | soundness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | well commented; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | removal of dead code; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | programming practices; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | delivery
process and environments. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Product Release (Code Delivery) | ||||||||||||||||||||||||||||||||||||||||||||||||||
| Standards for the Product Release are detailed in the Application Delivery Standards document on the Intranet. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Product Release is delivered as per Application Delivery Standards . The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Data Conversion Application is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | end users; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DBA and AA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Data Conversion Application will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | code structure conforms to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | soundness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | well commented; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | dead code; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | programming practices; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | delivery
process and environments. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | Two weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.6
QA OF IMPLEMENTATION PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| User Procedures Manual | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The User Procedures Manual provides the information and support
required for the End User. This document should be written using
"user friendly" terminology. It serves as the End User training
manual as well as the sole reference source for trained staff
using the system. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The User Procedures Manual is distributed via email or hardcopy
to the Information Management Business Analyst for the purpose
of being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the User Procedures Manual is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant business area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | end users; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information
Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The User Procedures Manual will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | readability; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | clarity; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | format. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | Two weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| User Acceptance Test Plan (UAT) | ||||||||||||||||||||||||||||||||||||||||||||||||||
User Acceptance Testing is part of the Implementation Phase in the SDLC (the 6th Phase in the SDLC). Ministry standards for testing are defined in the User Acceptance Test Standard. Note: The UAT Plan should be written by someone who understands the business. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The User Acceptance Test Plan (UAT) is distributed via email or
hardcopy to the Information Management Business Analyst for the
purpose of being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the UAT Plan is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The UAT Plan will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | must include plans for testing of Data Conversion Application (where required); | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | clarity and comprehension; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness for testing all requirements as described in the Software Requirements Specification Document; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness for covering all business scenarios and Exceptions. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Transition Plan (Includes Training) | ||||||||||||||||||||||||||||||||||||||||||||||||||
| Transition Plan is a detailed plan for moving from the current
application or manual procedures to the new application or upgraded
version. It should include plans for user training. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Transition Plan is distributed via email or hardcopy to the
Information Management Business Analyst for the purpose of being
quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Transition Plan is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant business area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Transition Plan will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | communications plan; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | fall back plan; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | training plan; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | details; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | timing; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | reasonability of time frames (e.g. system downtime); | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | resources
required. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Technical Documentation | ||||||||||||||||||||||||||||||||||||||||||||||||||
| Technical Documentation includes the system detail and support
documentation. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Technical Documentation is distributed via email or hardcopy
to the Information Management Business Analyst for the purpose
of being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Technical Documentation is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Ministry Project Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | AA and DBA for the technical QA; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Information Management BA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Technical Documentation will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | details; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | format; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | accuracy. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | One week. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.7
QA OF WAREHOUSE PHASE DELIVERABLES
|
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
4.8 QA of Deliverables During Maintenance Activities required after an application is successfully delivered into production are considered to occur during Maintenance. This is not a phase as such, but an ongoing process of updating or modifying an application because of bugs, service requests or other required changes. Depending on the activities involved, it may require some or all of the deliverables noted in the table below. Each deliverable should be quality assured as noted.
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Proposal - Annual | ||||||||||||||||||||||||||||||||||||||||||||||||||
The Project Proposal - Annual should be developed ahead of the annual planning process, or as needed throughout the year. For more details refer to the Ministry developed standard for the Project Proposal. The QA
processes for this deliverable are as defined in the Project
Proposal for the Planning Phase, but instead of being managed
by the Ministry Project Manager they are usually managed by
the Application Manager. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Cost Estimates | ||||||||||||||||||||||||||||||||||||||||||||||||||
| Cost Estimates are the process of estimating annual operational
support costs for an application. The Intranet has Guidelines
and a template to assist Application Managers with this process.
New systems should incorporate these guidelines during the Feasibility
phase of the project, to determine whether maintenance of the
system is economically feasible, and during the
Implementation phase, to confirm and adjust the estimated costs.
For existing systems the guidelines should be used annually to
re-evaluate support costs for the application, as these costs
can change over the life of an application. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The Cost Estimates are distributed via email to the Information
Management Business Analyst for the purpose of being quality assured. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the Cost Estimates is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant program area staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | business area specialist; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | relevant technical staff; | |||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The Cost Estimates will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry Standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | completeness; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | format. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | The QA results should be returned by the BA to Ministry Project Manager within 1 - 2 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Project Schedule - Annual | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The QA processes for this deliverable are defined in the Project
Schedule for the Planning Phase, but instead of being managed
by the Ministry Project Manager they are usually managed by the
Application Manager. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| CASE Repository - Update | ||||||||||||||||||||||||||||||||||||||||||||||||||
CASE (Computer-Assisted Software Engineering) Repository provides a central automated dictionary for storing and organizing all system information, including data definitions, diagrams, process specifications, and a variety of information related to planning project management, e.g., user access privileges and version control. A CASE repository also stores the relationships among the various information components, enabling sophisticated reports to be generated, e.g., the impact of design changes, or redundant data elements. The Ministry owns the CASE Repository and the Vendor must ensure the appropriate version is used. |
||||||||||||||||||||||||||||||||||||||||||||||||||
| Method of Delivery: | The
CASE Repository is delivered as per Application Delivery Standards. The vendor must ensure the
Ministry Project Manager or Application Manager receives notification
of delivery. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Performing the QA: | The QA of the CASE Repository is performed by: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | Application Manager; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | DA for the technical QA. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Scope of QA: | The CASE Repository will be quality assured for: | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | conformity to Ministry standards; | |||||||||||||||||||||||||||||||||||||||||||||||||
| — | content. |
|||||||||||||||||||||||||||||||||||||||||||||||||
| Timeframe: | Two weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| The Application Release | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The QA processes for this deliverable are as defined in the Product
Release for the Build Phase, but instead of being managed
by the Ministry Project Manager they are usually managed by the
Application Manager. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Updated System Documentation | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The QA processes for this deliverable are as defined in the Technical
Documentation for the Implementation Phase, but instead of
being managed by the Ministry Project Manager they are usually
managed by the Application Manager. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
| Updated End User Documentation | ||||||||||||||||||||||||||||||||||||||||||||||||||
| The QA processes for this deliverable are as defined in the User
Procedures Manual for the Implementation Phase, but instead
of being managed by the Ministry Project Manager they are usually
managed by the Application Manager. |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
5. CONCLUSION This guideline is intended to give Application Managers and developers an understanding of the Ministry's expectations and ensure a consistent approach to delivered products. |
APPENDIX A: QA MATRIX - DETAILED Quality
Assurance - Summarized by Phase/Deliverable The summary table below allows the user to navigate quickly through the QA processes and standards for each deliverable. The standard (if available) can be accessed by clicking on the deliverable name in Figure 2, below. The detailed QA processes can be accessed by clicking the "QA" button below the deliverable name in Figure 2. Note: This checklist is meant to be a quick reference only. Details as noted in section 4 should be followed for each deliverable. Also, where the time frame of 1 day is indicated, it means that a walkthrough or meeting is to be held to perform the QA on the deliverable. Where possible, the deliverable should be supplied in advance.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
A Guide to the Project Management Body of Knowledge - Project Management Institute Information Technology Project Management - Kathy Schwalbe (ISBN 0-7600-1180-X) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||