Bella Coola Valley Restoration
Objectives
To demonstrate a variety of restoration techniques
that would benefit a variety of salmonids at various life stages.
FRBC Region/ MELP Region/ MoF
Region
Pacific/Cariboo/Vancouver
Author
Michael A. Parker
Proponent
Ministry of Environment, with support of a Community
Partnership Group including, Department of Fisheries and Oceans,
Central Coast Regional District, International Forest Products,
Central Coast Fishermans Protective Association.
Watershed
Bella Coola
Location
The Bella Coola Watershed is located in the Mid
Coast Forest District approximately 450km West of the City of
Williams Lake.
Introduction
This project is the continuation of activities begun
on the ground in 1997. Through the participation of a local partnership
group small systems that feed the Bella Coola River are selected
for restoration activities. MELP staff has completed most of the
in stream prescriptions that are then constructed by a variety
of local firms and groups. Works have been intentionally kept
as primarily hand works when possible. The project created over
400 person days of work.
Assessments and Prescriptions
An Overview Fish Habitat Assessment was completed
for the Bella Coola Valley in 1996. Level 1 FHAPs were completed
on six different tributaries in 1997, and prescriptions have been
ongoing.
Rehabilitation Work
Site 1 - Anne Creek
Fencing was erected approximately 8 meters back
from the creek for 700 meters to eliminate cattle access. An alcove
pond into a corralled and graveled area provides a watering location
to the cattle away from the main channel. Hand crews removed all
small organic debris under 15 cm diameter and 2 meters in length
within the channel for 1100 meters. Rakes were used to remove
water parsnip that had choked the degraded channel. Finally, 846
Spruce and Cedar trees were planted within the newly fenced riparian.
Site 2 - Dump Creek
Dump Creek has historically been used as a spawning
and rearing area for Coho and Cutthroat. However, ongoing problems
with beaver and scour at a culvert placement on Highway 20 through
which the Creek flows limited access into and out of the upper
pond and channel portions of this creek. A beaver box was constructed
and installed on the upstream end of the culvert to prevent beavers
from damming the entrance, and a series of riffles were constructed
below the culvert to improve access to the culvert and the habitat
above. In the fall of 1998 adult Coho were observed in the pond
above the culvert having successfully negotiated the riffles and
beaver box.
Site 3 - Epp Creek
Epp Creek is a small channel primarily used for
Coho rearing. However, late summer low flows often stranded fish
in a few small pockets of water. A refuge pond of approximately
0.025 ha was excavated to a depth of 2 meters, and complexed with
rootwads, artificial cut banks, and other LWD placements. As well,
a 0.005 ha pond was excavated adjacent to a year round cool water
spring that augment water flows in the creek during low flow periods.
These two ponds will provide stable rearing and refugia area for
juvenile fish of many species that seek stability from the waters
of the Bella Coola mainstem some 300 meters downstream.
Site 4 - Tuck Creek
Tuck Creek was originally excavated as a 250 meter
drainage ditch through an old cutblock and agricultural land.
Due to the high quality of water it picked up, it has been highly
utilized by Pink, Chum, Coho, and Cutthroat, and to a lesser degree,
other species of fish. However, it is undersized for its high
flows, and has minimal habitat features. As the first step in
redesigning this channel, excavation has begun on a channel that
will bring more stable year round flows from a spring to the ditchline.
This 275 meter channel, to be built during early 1999, will have
a repeatable riffle pool morphology and be complexed with LWD
and boulder placements to target Steelhead and Cutthroat. In 1999,
this work will be connected to the spring and ditchline, and the
ditchline will be redesigned to handle all flows, complexed with
structures, and morphologically altered to provide a combination
of riffle and pool habitats. In total, 500 meters of new and existing
channel will be reworked and complexed.
Site 5 - Hagensborg Slough
Work on the Hagensborg Slough was a follow up to
restoration activities that had taken place during the summer
of 1997. A couple of days were spent checking the 47 structures
placed in 1997, and making any adjustments to these hand placements
as was necessary. In addition a pond and channel habitat from
one of the source springs was excavated to a depth of 2 meters,
with four pockets in an existing pond brought to a depth of 3
meters during 1998. This 0.04 ha area was complexed with LWD placements
and the streamside planted with 120 conifers. Coho, Cutthroat
and other species were counted through the fish fence being operated
as part of an ongoing monitoring program on the Slough. Over 400
spawning adult Coho were counted within the slough during the
fall of 1998. By far the largest numbers observed in recent years,
these fish were found almost exclusively within the reach restored
during the past two years.
Site 6 - George Hall Creek
George Hall Creek was set to receive 35, full spanning
log structures to promote scour of primary pool habitat within
500 meters of stream. Due to late funding approvals the in stream
window for this activity as missed. However, all logs and rock
materials have been placed on site and are ready for installation
in 1999.
Cost Summary
Labour NFOL $30,000
Labour non-NFOL $40,000
Expenses $18,500
Materials $19,000
Total $107,500
Proposed Work
Thirty five full spanning log placements will be
installed in George Hall Creek. Six large structures have been
designed for a 180 meter section of Nuhalk Creek. Activities will
continue in Anne Creek, George Hall Creek, Tuck Creek, Epp Creek,
and Hagensborg Slough. New activities will be undertaken in Fish
Creek, and Molly Walker Creek.
For Further Information contact:
Michael A. Parker
Ministry of Environment and Parks
400-640 Borland St.
Williams Lake, BC
V2G 4T1
Tel.(250)398-4696 Fax.(250)398-4214 |
Patricia
McKim Fletcher
Central Coast Regional District
P.O. box 186
Bella Coola, BC
V0T 1C0
Ph. 799-5291 Fax. 799-5750 |
Before shot of a beaver box installed on Dump Creek:

After shot of a beaver box installed on Dump
Creek:

Overwinter pond excavation on Epp Creek prior
to wood complexing:

Fish counting fence constructed on lower Hagensborg
Slough:
