Borthwick Creek Road Bridge Site
              Objectives
              To replace man-made barriers to fish with a clear 
                span structure.
              FRBC Region/ MELP Region/ MoF 
                Region
              Cariboo-Chilcotin/Cariboo/Cariboo
              Author
              Ken MacKenzie
              Proponent
              Weldwood of Canada Ltd.
                100 Mile House Operations
              Location
              The site is located at 0.5 km on the Borthwick Creek 
                Road in the Eagle Creek watershed. The unnamed stream flows into 
                Oie Creek.
              Introduction
              Rainbow trout are abundant in the steam as well 
                as a variety of non-game species.
              Assessments and Prescriptions
              The fish passage-culvert inspection report for the 
                Eagle Creek watershed identified this site as the highest priority 
                for restoration for a number of reasons. Habitat potential was 
                listed as high, the culverts were acting as a total barrier to 
                fish passage and a large amount of upstream habitat was isolated. 
                Two culverts at the site had water velocities of 1.5 m/s and outfall 
                drops of 25 cm (fig. 8-1).
              The width of the stream and quantity of spring flow 
                required that a bridge be prescribed to allow fish passage at 
                the crossing.
              Rehabilitation Work 
                 
              
 
                
                  - A dry environment during stream channel reconstruction was 
                    attained by diverting the stream into one of the existing 
                    culverts using a rock and filter fabric dam.
 
                  - Riprap was placed on all embankments to prevent erosion 
                    and sediment from entering the stream.
 
                  - An environmental monitor was on site during all phases of 
                    construction
 
                
               
              Structure Details  
              
 
                
                  - 12 meter concrete decked bridge (fig. 8-2)
 
                  - precast concrete footings with steel towers
 
                  - stream channel reconstructed to 3.5 meters
 
                
               
              Cost Summary
              Bridge design, supply and install $46,780
              Riprap, site plan and supervision $10,185
              Total $56,965 
              Environmental Benefits
              An additional 3.9 km of habitat is now available 
                to fish.
              For Further Information Contact:
              Ken MacKenzie
                P.O. Box 97
                Weldwood of Canada Ltd.
                100 Mile House Operations
                100 Mile House, BC
                V0K 2E0
                Tel. (250)395-8280
              Figure 8-1. Culvert prior to replacement.
              
               
              Figure 8-2. Final installation.
              