Canimred Creek Tributaries Bridge
Construction
Objectives
The primary objective of this project was to replace
a small culvert with a bridge to allow fish passage.
FRBC Region/ MELP Region/ MoF
Region
Cariboo-Chilcotin/Cariboo/Cariboo
Author
Ken MacKenzie
Proponent
Weldwood of Canada Ltd.
100 Mile House Operations
Location:
The crossing is located 2.0 km down a side road
at 17 km on the Bowers FSR at an unnamed stream that flows into
Canimred Creek.
Introduction
Canimred Creek has high densities of rainbow trout
and may be an important spawning stream for Canim Lake. The streams
affected by this project have high spawning and rearing habitat
potential.
Assessments and Prescriptions
This barrier to fish was identified during a field
inspection by Weldwood . The culvert was undersized for Q100 flows,
was quite long (25 meters), at a gradient that prohibited fish
passage and had a small outfall drop (fig. 3-1). A clear span
structure was determined to be the best option for restoring fish
passage.
Rehabilitation Work
To minimize environmental impacts during the weir
construction, the following steps were taken:
- A bypass channel was constructed adjacent to the culvert
that was armored with clean rock prior to stream diversion
(fig. 3-2).
- Riprap was placed at the upstream bend in the creek to eliminate
erosion and potential sediment inputs to the stream.
- Sediment traps of hay bales and filter cloth were placed
downstream to maintain water quality during channel reconstruction
work.
- An environmental monitor was on site for all phases of construction
Structure Details
- 15 meter concrete slab deck (fig. 3-3).
- 30° skewed approaches
- 8 inch steel posts on pre-cast concrete footings
- reconstructed channel width 4 to 5 meters
Cost Summary
Site Plan Preparation $2,000
Bridge design, supply and install $54,800
Rip rap supply, supervision $6,500
TOTAL $62,800
Environmental Benefits
2.4 km of habitat is now available to fish.
For Further Information Contact:
Ken MacKenzie
P.O. Box 97
Weldwood of Canada Ltd.
100 Mile House Operations
1 00 Mile House, BC
V0K 2E0
Tel. (250)395-8200
Figure 3-1. Outfall of culvert

Figure 3-2. Construction of bypass channel.

Figure 3-3. Completed installation
