Canimred Tributary Weir Construction
535 Road
Objectives
The primary objective of this project was to construct a weir
to allow fish passage through existing culverts increasing the
quantity of available habitat.
FRBC Region/ MELP Region/ MoF Region
Cariboo-Chilcotin/Cariboo/Cariboo
Author
Ken MacKenzie
Proponent
Weldwood of Canada Ltd.
100 Mile House Operations
Location:
The crossing is located 0.5 km down a side road at 17 km on the
Bowers FSR at an unnamed stream that flows into Canimred Creek.
Introduction
Canimred Creek has high densities of rainbow trout and may be
an important spawning stream for Canim Lake. The streams affected
by this project have high spawning and rearing habitat potential.
Assessments and Prescriptions
This barrier to fish was identified during a field inspection
by Weldwood staff. It was determined during the site plan preparation
that the existing culverts were sufficiently large to accommodate
the Q100 flows. The primary barrier to fish was caused by the
20 cm outfall at the downstream end of the culverts and increased
water velocity during high flow periods (fig 2-1). Constructing
weirs to eliminate the outfall drop barrier was determined to
be the most cost effective solution.
Rehabilitation Work
To minimize environmental impacts during the weir construction,
the following steps were taken:
- Only clean rock was used for construction of the weir to reduce
sediment input into the stream.
- An environmental monitor was on site for all phases of construction
Structure Details
Two weirs were built to eliminate the outfall drop from the culverts.
The first weir raised water levels at by approximately 30 cm slowing
water velocities through the culverts and eliminating the outfall
drop. An additional benefit from the weir construction is the
significant deepening of the plunge pool for overwintering habitat.
A second smaller weir was built downstream from the first to reduce
the gradient of the stream and provided better fish passage.
Cost Summary
Site Plan Preparation $2,000
Rip rap supply $4,500
Supervision $2,000
Machine Time $1,500
TOTAL $10,000
Environmental Benefits
6.2 km of habitat is now available to migrating rainbow trout.
For Further Information Contact:
Ken MacKenzie
P.O. Box 97
Weldwood of Canada Ltd.
100 Mile House Operations
100 Mile House, BC
V0K 2E0
Tel. (250)395-8280
Figure 2-1. Culverts prior to weir construction

Figure 2-2. Culverts backflooded after weir installation.
