Kwatna River Overwinter Pond 
                  Project - Gus Creek
                 
                Objectives
                To establish rearing and high water refuge in 
                  the lower reaches of the Kwatna River for Coho.
                FRBC Region/ MELP Region/ 
                  MoF Region
                Mid Coast/Cariboo/Mid Coast
                Author
                Niel Oborne, International Forest Products and 
                  Michael A. Parker, MELP
                Proponent
                International Forest Products, Mid Coast Division, 
                  Hagensborg, BC
                Watershed
                Kwatna River
                Location
                The project area is located within the Mid Coast 
                  Forest District of the MELP Cariboo Region, some 55 km West 
                  of the community of Bella Coola.
                Introduction
                The Gus Creek site is an old back channel that 
                  has been in filled by silt. It is located low on the watershed 
                  ( 3 km. from the estuary ) and downstream of approximately 90 
                  % of the spawning sites. The channel is still within tidal influence 
                  and twice / day for at least 20 days / mo. is enhanced by tidal 
                  flows.
                Assessments and Prescriptions
                This project follows 3 yrs. of up slope watershed 
                  restoration activity in the Kwatna watershed. Fish Habitat Assessments 
                  indicated that rearing habitat is a limiting factor in our efforts 
                  directed toward restoration of fish population to near historical 
                  levels. An Overview and Level 1 Fish Habitat Assessments were 
                  completed by Grizzly Holdings Ltd. on the Kwatna River in 1997. 
                  In 1998, LGL Ltd. completed Level 2 FHAP prescriptions for several 
                  sites on the Kwatna. Due to the late start in the restoration 
                  season in 1998, the Gus Creek Off Channel was undertaken as 
                  it could be constructed in the dry and only connected once completed. 
                
                Rehabilitation Work
                Interfor chose an EX200 excavator owned by the 
                  local Nuxalk Band with an operator adept in logging road construction, 
                  landscaping, and pond building. A Clark 668C line skidder owned 
                  by Tim Case, Hagensborg, was hired to transport large wood debris 
                  to the site. The labour crew varied from 1 to 3 persons. To 
                  account for our presence and activity in a sensitive riparian 
                  area and adjacency to a major salmon producing stream Bio Forest 
                  Consulting Services was retained to do environmental monitoring 
                  for the project.
                The project began in Sept. / 98 and continued 
                  through to Nov. / 98. Midway through this period we finished 
                  excavating the suggested channel according to LGLs prescriptions. 
                  It was agreed between Interfor, MELP, and LGL that considering 
                  cost and the amount of pond habitat built that is would be better 
                  to double the size of the Gus Creek project than to move on 
                  to the next project which had a few unknowns built into it.
                The average mid pond depth is approx. 2 meters 
                  at low tide, high tide may increase this depth by as much as 
                  1 meter. Over 200 individual pieces of wood debris were anchored 
                  or placed in the pond to serve as cover. Final completion is 
                  scheduled for Mar. / 99 when all bared soil will be seeded with 
                  a coastal reclamation grass mixture young cedar and spruce trees 
                  will be planted to increase riparian cover.
                Work to date created 356 person days of labour.
                Cost Summary
                 
                  
                     
                      | Machinery | 
                       
                         $77,500 
                        | 
                    
                     
                      | Materials (found on 
                        site) | 
                       
                         nil 
                        | 
                    
                     
                      | Labour | 
                       
                         $60,300 
                        | 
                    
                     
                      | Total | 
                       
                         $137,800 
                        | 
                    
                  
                 
                 
                Restoration Results
                The completed Overwinter pond is 420 lineal meters 
                  and is slightly over 0.5 ha. (500m2) in surface area. 
                  The average mid channel depth is approximately 2 meters at low 
                  tide, high tide may increase this depth by as much as 1 meter. 
                  Nearly 100 individual pieces of wood debris were anchored or 
                  placed in the pond to serve as cover.
                Biostandards suggest that this pond should supply 
                  new habitat to 340 adult Coho, and some 6000 smolts (Keely et 
                  al. 1996, and Adams and Whyte 1990 as cited in Slaney and Zaldokas 
                  1997). An estimated 2072 salmonid fish would be expected in 
                  the 0.5ha pond given the equation Log10 fish number 
                  = 0.51 log10 pond area(ha)+3.47 (Keely and Slaney 
                  1996 as cited in Slaney and Zaldokas 1997) for overwinter ponds.
                Proposed Work
                There are several other sites including wood complexing 
                  and rearing pond development within the Kwatna River watershed 
                  for which prescriptions have already been drawn. These are scheduled 
                  to be completed during the in stream window of 1999. As well, 
                  seeding and riparian planting along the created off channel 
                  will be completed in 1999.
                For Further Information contact:
                 
                  
                     
                      Niel Oborne 
                         
                        International Forest Products 
                        P.O. Box 50 
                        Hagensborg, BC 
                        V0T 1H0 
                        WRP Coordinator 
                        Tel. (250)-982-3226  
                       | 
                      Michael A. Parker  
                        Ministry of Environment and Parks 
                        400-640 Borland St. 
                        Williams Lake, BC 
                        V2G 4T1 
                        Tel.(250)398-4696 Fax.(250)398-4214  
                       | 
                    
                  
                 
                
                  
                Off channel rearing pond excavated along 
                  Kwatna River mainstem prior to LWD complexing and planting of 
                  broadcast overburden materials.
                 
                  Literature cited:
                  Slaney, P.A. and D. Zaldokas (eds.). 1997. Fish 
                    Habitat Rehabilitation Procedures. Watershed Restoration Technical 
                    Circular No. 9. ISBN 0-7726-3320-7. Ministry of Environment 
                    Lands and Parks. Vancouver, BC.