Lorin Lake Bridge 8200 Road
Objectives
The primary objective of this project was to remove
man-made barriers to fish passage allowing migrating fish access
to increased habitat. A second objective was to reduce the risk
of sediment delivery into the stream.
FRBC Region/ MELP Region/
MoF Region
Cariboo-Chilcotin/Cariboo/Cariboo
Author
Ken MacKenzie
Proponent
Weldwood of Canada Ltd.
100 Mile House Operations
Location:
The crossing is located at 14.5 km on the Bowers
Lake Forest Service Road (8200 Road) at an unnamed stream which
flows from Lorin Lake into Cougar Creek.
Introduction
Both Lorin Lake and Cougar Lake are popular fishing
lakes and receive moderate to high fishing pressure throughout
the fishing season. Rainbow trout are the only game fish found
in this system.
Assessments and Prescriptions
The Jim-Windy Watershed fish passage culvert
inspection report identified this site as the top priority for
restoration in this watershed for a number of reasons. The culvert
at the crossing was a complete barrier to fish passage by increasing
water velocity (velocity on June 6, 1998 was 1.81 m/s) and because
of an outfall drop of 25 cm. The stream has good potential spawning
substrate and is the main upstream tributary for Cougar Lake.
The culvert was undersized and had the potential to become plugged
which may have resulted in a serious road washout and considerable
sediment delivery into the stream.
Because of the relatively steep slope of the stream
at the crossing site (6.5%), the best option to restore fish
passage was deemed to be a clear-span structure. A permanent,
concrete decked bridge was prescribed because the Bowers Lake
FSR is a well used main haul road.
Rehabilitation Work
To minimize environmental impacts during the culvert
replacement work, the following steps were taken:
- Flow was blocked into the culvert using rock and filter
fabric so that all work was performed in a dry environment.
- Water was pumped around the culvert into the plunge pool
at the outfall using fire-fighting water pumps during installation.
- Water was pumped into barrels to reduce water velocities
to prevent scour and sediment generation in the stream.
- Sediment traps of hay bales and filter cloth were installed
downstream of the pump discharge.
- An environmental monitor was on site for all phases of
construction
Structure Details
- 9.1 meter concrete deck composite design (fig. 1-2).
- pre-cast concrete footing with 8 inch steel towers.
- bridge deck at 3% slope.
- reconstructed channel width 2.5 meters.
Cost Summary
Design, supply and install bridge $47,500
Rip rap supply $2,500
Supervision $2,000
TOTAL $52,000
Environmental Benefits
Rainbow trout from Cougar Lake now have unrestricted
access to an additional 1.5 km of spawning stream to Lorin Lake
in addition to Lorin Lake itself and the small streams that
drain into it . This more than doubles the available upstream
habitat from Cougar Lake. The trout population in Lorin Lake
is no longer isolated from the remainder of the watershed.
For Further Information Contact:
Ken MacKenzie
P.O. Box 97
Weldwood of Canada Ltd.
100 Mile House Operations
100 Mile House, BC
V0K 2E0
Tel. (250)395-8280
Figure 1-1. Channel is constructed to
route stream prior to pulling culvert on unnamed creek.

Figure 1-2. Completed 8200 road bridge
installation.
