Rebman Creek Rock Riffle Construction
              Objectives
              The objectives of this project are to reestablish 
                pool riffle morphology within the system. Minimal existing pool 
                habitat was determined to be a detriment to low flow refuge and 
                to rearing capabilities of the system. Reestablishment of a higher 
                percentage of pool area is the primary objective.
              FRBC Region/ MELP Region/ MoF 
                Region
              Cariboo/Cariboo/Cariboo
              Author
              Michael Parker 
              Proponent
              Weldwood of Canada Ltd., Quesnel Division
              Watershed
              Rebman Creek
              Location
              Rebman Creek is a tributary to the Willow River. 
                Located in the Quesnel Forest District, it lies approximately 
                100km Northeast of the City of Quesnel.
              Introduction
              Rebman Creek is approximately 3m bankfull in width 
                with a gradient ranging 3-6%. It is a rearing area and high water 
                refuge for fish from the mainstem Willow River. An extremely high 
                (>53%) proportion of the watershed has been logged, with much 
                of it leaving little to no riparian area. Pool habitat was approximately 
                3% over the first 4 reaches. LWD was extremely limited. Extreme 
                low flows in August often cause the first reach to go dry, and 
                lack of pools in the upper reaches cause a variety of problems 
                from thermal warming, predation, crowding, etc. during low flow 
                periods.
              Assessments and Prescriptions
              As part to the Willow River Watershed, Rebman has 
                been subject to Overview and Level 1 Fish Habitat and Riparian 
                Assessments completed in early 1998 by LGL Ltd. Level 2 Assessments 
                were conducted during the fall of 1998. Many upslope assessments 
                have also been completed and road deactivation and slope stabilization 
                projects were underway during the fall of 1998.
              Rehabilitation Work
              Given the late start of in stream works in Rebman, 
                six consecutive sites in Reach 4 were prescribed for works during 
                the fall of 1998. The remaining 40+ will be completed in 1999. 
                This years work consisted of the construction of rock riffles 
                using local materials and a hand crew from Randall and Associates. 
                This crew pioneered a technique of using compressed air to loosen 
                impacted substrates, freeing the rocks necessary to construct 
                the riffle and pool sequence. This technique appeared to be successful 
                in execution, and will therefore likely be used in the coming 
                year to eliminate riparian damage that would be caused by using 
                a machine. This was deemed important as regeneration of riparian 
                was providing the primary cover along the mainstem. Fish salvage 
                was conducted prior to construction of individual structures.
              Cost Summary
               
                
                   
                    |  
                       Item 
                      | 
                     
                       Cost 
                      | 
                  
                   
                    | Materials | 
                     
                       $4,577 
                      | 
                  
                   
                    | Labour | 
                     
                       $9,350 
                      | 
                  
                   
                    | Machinery | 
                     
                       nil 
                      | 
                  
                   
                    | Total | 
                     
                       $13,927 
                      | 
                  
                
               
 
              Restoration Results
              Six structures were completed over a test section 
                of approximately 200 meters of stream. Reevaluation of these hand 
                constucted structures that utilized on site materials will be 
                done in the spring, and a determination made if it is necessary 
                to use machinery and / or imported materials to complete remaining 
                structures. 
              Proposed Work
              Approximately 40 remaining riffle structures and 
                bank stabilization efforts are to be completed during the 1999 
                season.
              For Further Information contact:
               
                
                   
                    Michael A. Parker 
                       
                      Ministry of Environment and Parks 
                      400-640 Borland St. 
                      Williams Lake, BC 
                      V2G 4T1 
                      Tel.(250)398-4696 Fax.(250)398-4214  | 
                    Gerry Powell  
                      FRBC Projects Manager 
                      Weldwood of Canada Ltd. 
                      P.O. Box 2000 
                      Quesnel, B.C. V2J 3J5 
                      Ph. 747-2862  | 
                  
                
               
              
              Hand constructed rock riffle completed on Rebman 
                Creek mainstem, Willow River watershed.