Rebman Creek Rock Riffle Construction
Objectives
The objectives of this project are to reestablish
pool riffle morphology within the system. Minimal existing pool
habitat was determined to be a detriment to low flow refuge and
to rearing capabilities of the system. Reestablishment of a higher
percentage of pool area is the primary objective.
FRBC Region/ MELP Region/ MoF
Region
Cariboo/Cariboo/Cariboo
Author
Michael Parker
Proponent
Weldwood of Canada Ltd., Quesnel Division
Watershed
Rebman Creek
Location
Rebman Creek is a tributary to the Willow River.
Located in the Quesnel Forest District, it lies approximately
100km Northeast of the City of Quesnel.
Introduction
Rebman Creek is approximately 3m bankfull in width
with a gradient ranging 3-6%. It is a rearing area and high water
refuge for fish from the mainstem Willow River. An extremely high
(>53%) proportion of the watershed has been logged, with much
of it leaving little to no riparian area. Pool habitat was approximately
3% over the first 4 reaches. LWD was extremely limited. Extreme
low flows in August often cause the first reach to go dry, and
lack of pools in the upper reaches cause a variety of problems
from thermal warming, predation, crowding, etc. during low flow
periods.
Assessments and Prescriptions
As part to the Willow River Watershed, Rebman has
been subject to Overview and Level 1 Fish Habitat and Riparian
Assessments completed in early 1998 by LGL Ltd. Level 2 Assessments
were conducted during the fall of 1998. Many upslope assessments
have also been completed and road deactivation and slope stabilization
projects were underway during the fall of 1998.
Rehabilitation Work
Given the late start of in stream works in Rebman,
six consecutive sites in Reach 4 were prescribed for works during
the fall of 1998. The remaining 40+ will be completed in 1999.
This years work consisted of the construction of rock riffles
using local materials and a hand crew from Randall and Associates.
This crew pioneered a technique of using compressed air to loosen
impacted substrates, freeing the rocks necessary to construct
the riffle and pool sequence. This technique appeared to be successful
in execution, and will therefore likely be used in the coming
year to eliminate riparian damage that would be caused by using
a machine. This was deemed important as regeneration of riparian
was providing the primary cover along the mainstem. Fish salvage
was conducted prior to construction of individual structures.
Cost Summary
Item
|
Cost
|
Materials |
$4,577
|
Labour |
$9,350
|
Machinery |
nil
|
Total |
$13,927
|
Restoration Results
Six structures were completed over a test section
of approximately 200 meters of stream. Reevaluation of these hand
constucted structures that utilized on site materials will be
done in the spring, and a determination made if it is necessary
to use machinery and / or imported materials to complete remaining
structures.
Proposed Work
Approximately 40 remaining riffle structures and
bank stabilization efforts are to be completed during the 1999
season.
For Further Information contact:
Michael A. Parker
Ministry of Environment and Parks
400-640 Borland St.
Williams Lake, BC
V2G 4T1
Tel.(250)398-4696 Fax.(250)398-4214 |
Gerry Powell
FRBC Projects Manager
Weldwood of Canada Ltd.
P.O. Box 2000
Quesnel, B.C. V2J 3J5
Ph. 747-2862 |

Hand constructed rock riffle completed on Rebman
Creek mainstem, Willow River watershed.