Spanish Creek Tributary Culvert
Replacement 7000 Road
Objectives
To replace a series of culverts that are acting
as a barrier to fish movement and to reduce the risk of sediment
delivery to Spanish Creek.
FRBC Region/ MELP Region/ MoF
Region
Cariboo-Chilcotin/Cariboo/Cariboo
Author
Ken MacKenzie
Proponent
Weldwood of Canada Ltd.
100 Mile House Operations
Location
The site is located at 31 km on the 7000 Road just
south of Spanish Lake and west of Wells Gray Park on an unnamed
tributary to Spanish Creek.
Introduction
This stream is one of the main tributaries to upper
Spanish Creek and has relatively high densities of rainbow trout
downstream of the culverts.
Assessments and Prescriptions
This site was listed as the highest priority crossing
for restoration in the Deception/Spanish watershed in the Boss-Deception
fish passage-culvert inspection report. 4 culverts existed at
the crossing all of which were barriers to fish passage due to
high flow velocities and outfall drops (fig. 4-1). The site was
a potential sediment source as well due to high flows and insufficient
culvert capacity.
The 10 meter width of the stream required that a
clear span structure be used to provide fish passage and accommodate
spring flow volumes.
Rehabilitation Work
- Silt fences were placed downstream of the works to maintain
water quality during construction.
- Water was diverted into a single culvert while the remainder
were removed and a new channel was constructed.
- And environmental monitor was on site during all phases
of construction
Structure Details
- 18 meter concrete deck composite design (fig 4-2)
- pre-cast concrete footings with 12 inch steel towers
- 3% slope to deck
- reconstructed stream channel approximately 10 meters wide
Cost Summary
Bridge design, supply and install $65,917
Riprap, site plan and supervision $16,820
Total $82,737
Environmental Benefits
Reduced risk of serious sediment introduction into
Spanish Creek from a road washout due to blocked culverts. Fish
access to 6.3 km of additional habitat.
For More Information Contact:
Ken MacKenzie
P.O. Box 97Weldwood of Canada Ltd.
1 00 Mile House Operations
100 Mile House, BC
V0K 2E0
Tel. (250) 395-8280
Figure 4-1. Culverts prior to replacement.

Figure 4-3. Final Installation
