Talchako River Groundwater Channel
Objectives
To restore access to existing offchannel habitat
and restore groundwater off channel habitat in the Talchako River
for overwinter and high flow refuge for Coho and Cutthroat.
FRBC Region/ MELP Region/ MoF
Region
Vancouver Island/Cariboo/Vancouver Island
Author
Michael Parker , MELP
Proponent
International Forest Products, Mid Coast Division,
Hagensborg, BC
Watershed
Talchako River
Location
Talchako River partially defines Tweedsmuir Provincial
Parks South West boundary. It is located approximately 380
km West of the City of Williams Lake and 60 km East of the community
of Bella Coola. Along with the Atnarko River it forms the Bella
Coola River.
Introduction
All significant tributaries to the Talchako are
glacial fed and limited to fish access by gradient within less
than 1 km. The Talchako itself is highly glacial with very little
offchannel habitat. Several offchannel ponds and groundwater channels
exist between 72-84 km. As most of these run parallel to the mainstem
on the valley floor, they were areas that were logged over. Beaver
activity has also prevented access to several of these high value
clear water areas.
Assessments and Prescriptions
In 1996 a Overview and Level 1 Assessment was completed
for the Bella Coola River including the Talchako and some of its
major tributaries. In 1998, further Level 1 Assessments were completed
on several of the small groundwater channels and off channel habitat
in the upper regions of the watershed.. Ministry of Environment
completed prescriptions for SOD removal through old cutblocks,
access structures around beaver dams and groundwater channel excavation
to reopen and enhance areas within cutblocks.
Rehabilitation Work
On the ground activities can be divided into
three:
- SOD removal was carried out in three cutblock locations
along small groundwater channels to improve flow and scour.
These clearwater channels were full of past logging slash.
Over 550 linear meters of channel was hand cleared at three
different sites. Any material under 15 cm diameter and/or
2 meters in length was removed from the channels. All large
material was left in place.
- Groundwater channel excavation was carried out
at one location during 1998. Roughly 200 meters of channel
was excavated to redefine stream banks and establish deep
pond areas in an area that had seen past impacts from skidding
and other logging activities. This channel was typically excavated
2meters wide and 1 meter deep, with meanders, pools and pond
areas. LWD was reestablished to the channel and ponds and
keyed into the banks. As flows are stable through this groundwater
area, no cable anchoring was employed.
- A hand dug channel was established around a deserted
beaver dam to gain access to nearly 1 km of groundwater channel
and rearing pond area. The 20 meter long channel consisted
of a series of step pools that dropped in total 0.8 meters.
Each step was no more than 15 cm to ensure access of juvenile
target species to the habitat upstream. The channel was lined
with filter fabric and covered with an assortment of angular
substrate. Rock / log structures created the plunge pools
and were keyed to the banks for stability. Minimal riparian
impact was created through the use of hand construction and
a variety of local sedges, conifers and other vegetation transplanted
to the edge of the channel. As the beaver dam itself created
a high value pond habitat heavily complexed by mature LWD,
it was a feature that should be maintained for a long period.
Therefore, plastic was placed along the dam on the upstream
side to ensure all water goes through the created side channel
and would not percolate through the dam at lower flows. The
plastic was then covered with soil and rock to hold it in
place, and the whole dam covered with soils to promote vegetative
growth, and establish the dam as a permanent feature. A small
rip rapped overflow channel was created to handle any excessively
high flows.
Cost Summary
Item
|
Cost
|
Machine |
$22,200
|
Materials |
$2,600
|
Labour |
$110,000
|
Total |
$134,800
|
Restoration Results
Within two hours of completing the beaver dam by
pass channel one juvenile Coho and one Cutthroat were into the
second step pool. By the next day fish were found throughout the
steps. Minnow traps will be set in the pond and channel above
in 1999 to examine distribution and species.
Removal of SOD created a visible increase in localized
stream velocities and scour of fine in some areas was revealing
buried cobble and gravel substrate.
Groundwater channel excavation was not completed
at the time of writing this report.
Proposed Work
Further groundwater channel excavation and complexing
is anticipated at three locations for 1999. Access problems at
two long abandoned beaver dams will also be evaluated and prescriptions
written.
For Further Information contact:
Michael A. Parker
Ministry of Environment and Parks
400-640 Borland St.
Williams Lake, BC
V2G 4T1
Tel.(250)398-4696
Fax.(250)398-4214 |
Or |
Niel Oborne
International Forest Products
P.O. Box 50
Hagensborg, BC
V0T 1H0
WRP Coordinator
Ph.982-3226 |
Initial hand excavation of beaver dam by pass
channel, Talchako River, 77km.

Same section of by pass channel with flow and vegetated
banks, Talchako River 77km.
Portion of excavated groundwater channel at 77km,
Talchako River prior to LWD complexing.